Campinas: a data-center inquiry

In Campinas, the São Paulo Public Prosecutor's environmental group GAEMA opened a civil inquiry on 15 September into the water, power and urban effects of TERRANOVA's planned AI and cloud campus on the former Fazenda Pau d'Alho [V-s] (G1; Correio). The prefecture says the data center itself is not licensed, only a substation; the company, a hyperscale platform launched by Actis, says it will use closed-loop liquid cooling and will answer the prosecutor [V-s] (same sources). Company and trade figures put the first phase at more than US$500 million and about 216 MW of IT capacity [V-s] (G1, 20 August; Intelligent CIO). A peak-use water figure of 3.24 million litres a day appears in filings under review, not as a measured volume [V-s] (same G1, 17 September). A 12-year municipal tax package, under Law 16.174/2021, has been reported as granted in April [V-s] (Correio; the statute is Law 16.174/2021). The inquiry is not a finding of irregularity.